Under the Construction (Design and Management) Regulations 2015, who is responsible for providing pre-construction information?

Prepare for the CITB Health, Safety and Environment (HSE) Managers and Professionals (MAP) Test. Access comprehensive questions and detailed explanations to enhance your understanding. Get ready for success!

The responsibility for providing pre-construction information under the Construction (Design and Management) Regulations 2015 lies with the client. This regulation mandates that the client must ensure that relevant information is gathered and provided to the designers and contractors before the construction phase begins.

The purpose of pre-construction information is to give adequate details about the project, including potential risks, to ensure that those involved in the design and construction can make informed decisions that promote health and safety from the outset. This proactive approach is crucial as it helps to mitigate risks associated with construction work and ensures that safety considerations are integrated into the project from the planning stage.

While other parties such as the contractor, project manager, and health and safety officer play important roles in health and safety compliance during the project, the primary legal responsibility for compiling and providing pre-construction information rests with the client according to the regulations.