Where would you find the method for controlling identified hazards on a demolition project?

Prepare for the CITB Health, Safety and Environment (HSE) Managers and Professionals (MAP) Test. Access comprehensive questions and detailed explanations to enhance your understanding. Get ready for success!

The method for controlling identified hazards on a demolition project would be found in the construction phase plan. This document is essential for outlining how the project will be carried out safely, including specific measures to manage risks identified during the risk assessment. The construction phase plan addresses site-specific hazards, detailing the approach to risk management, safety protocols, emergency procedures, and resource allocation necessary to ensure the health and safety of workers and others affected by the demolition work.

Other documents mentioned, such as the risk assessment report, primarily identify and analyze hazards rather than specify control methodologies in a direct manner. The health and safety policy manual serves as a broader framework for safety practices but does not address project-specific controls in detail. While project management guidelines may involve planning aspects, they usually do not delve into hazard control measures required during the execution of demolition activities.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy